Railway

Looking at the railway I estimated the following timeline.

Week 1 – Infastructure (Date Range):
This week is time to just prepare all infastructure
This includes clay mines.

Week 2 – Build Platform – Stage 1 (Date Range):
Prepare Materials – 4 Days
Prepare 5000 KG Stone
Prepare 2000 KG Clay
Prepare 4000 Bricks

  1. 12000 KG Clay
  2. 3000 KG Coal
  3. 16000 Minutes of work (Spade and Shovel)

Prepare 1500 Clay Tiles

  1. 4500 KG Clay
  2. 1500 KG Coal
  3. 6000 Minutes of Work (Spade and Shovel)

Prepare 1000 Wooden Girders

  1. 25000 KG Wood
  2. 25000 Minutes of Work (Axe Only) **Heaviest, Week 1

Prepaire 5000 Nails

  1. 100 KG Ore
  2. 50 KG Coal
  3. 5000 Minutes of Work (Sledgehammer and Shovel)

Build Platform:

  1. 400 000 Minutes of Work (Axe and Saw)

Week 3, 4, 5 & 6 – Build Railway (Stage 2) (Date Range):

Prepare Materials – 11 Days
Prepare 3000 Rail Tie

  1. 450 000 KG Wood
  2. Work is Trolleymaster ONLY
  3. 450 000 Minutes of Work (Axe and Chisel)

Prepare 650 000 pieces of Stone Rubble

  1. 975 000 KG Stone
  2. Work is Stone Mason ONLY
  3. 1300000 Minutes of work (Sledgehammer and Shovel) **Heaviest, Start in Week 1

Prepare 12 000 Tie Knotters

  1. 12000 KG Ore
  2. 6000 KG Coal
  3. 6000 KG Clay
  4. Work is Metalurgist Only
  5. 24000 Minutes of work (Sledgehammer and Hammer)

Prepare 1200 Iron Rails

  1. 150 000 KG Ore
  2. 75 000 KG Coal
  3. 75 000 KG Clay
  4. Work is Metalurgist Only
  5. 360 000 Minutes of work (Sledgehammer and Shovel)

Build Railway

  1. 1 700 000 Minutes of Work (Sledgehammer and Shovel)

Week 7 – Build Train (Stage 3) (Date Range):

Prepare 50 Steel Plates

  1. 5000 KG Ore
  2. 2500 KG Clay
  3. 2500 KG Coal
  4. Work is Metalurgist Only
  5. 10 000 Minutes of Work (Sledgehammer and Shovel)

Prepaire 3000 Nails

  1. 60 KG Ore
  2. 30 KG Coal
  3. 3000 Minutes of Work (Sledgehammer and Shovel)

Prepare 1000 Steel Plates

  1. 2000 KG Ore
  2. 1000 KG Coal
  3. 1000 KG Clay
  4. 4000 Minutes of work (Sledgehammer and Shovel)

Prepare 400 Wooden Girders

  1. 10000 KG Wood
  2. 10000 Minutes of Work (Axe Only)

Prepare 1000 Wood Planks

  1. 8000 KG wood
  2. 8000 Minutes of Work (Saw Only)

Build Train

  1. 400 000 Minutes of Work (Sledgehammer and Saw)

Week 8 & 9 – Tieing up loose ends